PROJECT MILESTONES ACHIEVEMENT AT A GLANCE…..
2018
Commercial Operations Date
15th March, 2018
Reliability Run Test
08th March, 2018
2017
Plant Energization Date
31st January, 2017
2016
Commencement of Construction
02nd November, 2016
Project Kick-off Meeting
28th September, 2016
Financial Close
08 August, 2016
Implementation Agreement
2nd August, 2016
A&R EPA Execution
28th July, 2016
Site Sub-Lease Agreement (2)
25th July, 2016
2015
1st Extension in LOS issued
17 December, 2015
Award of Upfront Tariff (2)
10th August, 2015
EPA Execution
10 March, 2015
2014
LOS issued
19 November, 2014
Term Sheet signed with OPIC
18th July, 2014
Award of Upfront Tariff (1)
20th June, 2014
2nd Extension in LOI issued
16th May, 2014
2013
1st Extension in LOI issued
23rd October, 2013
2012
Site Sub-Lease Agreement (1)
27th November, 2012
LOI issued
6th February 2012