PROJECT MILESTONES ACHIEVEMENT AT A GLANCE…..

2018
March 15

Commercial Operations Date

15th March, 2018
March 8

Reliability Run Test

08th March, 2018
2017
January 31

Plant Energization Date

31st January, 2017
2016
November 2

Commencement of Construction

02nd November, 2016
September 28

Project Kick-off Meeting

28th September, 2016
August 8

Financial Close

08 August, 2016
August 2

Implementation Agreement

2nd August, 2016
July 28

A&R EPA Execution

28th July, 2016
July 25

Site Sub-Lease Agreement (2)

25th July, 2016
2015
December 17

1st Extension in LOS issued

17 December, 2015
August 10

Award of Upfront Tariff (2)

10th August, 2015
March 10

EPA Execution

10 March, 2015
2014
November 19

LOS issued

19 November, 2014
July 18

Term Sheet signed with OPIC

18th July, 2014
June 20

Award of Upfront Tariff (1)

20th June, 2014
May 16

2nd Extension in LOI issued

16th May, 2014
2013
October 23

1st Extension in LOI issued

23rd October, 2013
2012
November 27

Site Sub-Lease Agreement (1)

27th November, 2012
February 6

LOI issued

6th February 2012